MiniBooNE Phototube Support Structure Installation

Fermilab Visual Media Services made a nice little documentary about the installation of the detector.

  • January 5, 2001: installation work in tank began.
  • Feb 22: first PMT installed.
  • May 15: we reach the equator.
  • Jul 20: all but polar caps and access rows complete.
  • Sep 7: polar caps installed.
  • Oct 19: last PMT's installed.
  • 1521 PMT's installed and tested in total.
pdm_neg15a.jpg
neg60-25a.jpg

 

 

 

 

 

 

This web page will documents the installation of experimental equipment inside the MiniBooNE detector tank. For an overview of the MiniBooNE experiment and links to general information about neutrinos and neutrino oscillations, see the MiniBooNE page at Fermilab 

 

Dsc00002a.jpg
 
P1010081.JPG

 

Feb 5-9: Surveying for lat installation.

Crack Princeton alignment group setting up laser level.
survey1b.jpg
Laser level (note red line on tank wall) is used to position the clamp ends of a row of struts. The vertical yellow measuring tape is our height standard, referenced to the average of a number of surveyed bosses.
survey2b.jpg
Strut mounted on boss on tank wall. The length of the strut is determined by the boss survey. The strut is then pivoted on its base to align the clamp with the laser.
strut.jpg
  
First lat section installed on struts.
lat1.jpg
First lat in place.
lat2.jpg

Feb 12-16: Lat 0-6 installation.

Several lats in place. This is a quite striking view!
lat3.jpg
Bill Sands with newly-installed Lat 0. Unlike the rest, Lat 0's struts are suspended from I-beams in the tophat.
lat4.jpg

Feb 19-23: Hardware and first phototubes.

Quadrant view, showing (top to bottom): cable bundles, main strain relief, boss/strut/clamp, lat, lat strip with overlap panel.

 

MVC-441X.JPG

 

 

 

Bill and Hayes with test installation of first optical barrier panel.
MVC-439X.JPG

 

Lats 1-4 with lat strips and test installation of two OB panels.
MVC-442X.JPG
OB panel with two PMT stands. Mounting blocks change orientation to accept both stand types. (Don't tell Bonnie till we find those tubes!)
MVC-445X.JPG
First phototubes mounted!! Veto cluster 2-1 on the tank wall.
Mvc-443xadj.jpg

 

Another view of veto cluster 2-1.
MVC-444X.JPG
Stan making first splice on veto tube 2-1A.
MVC-446X.JPG
First splice with oil seal.
MVC-449X.JPG
Testing splice 2-1B: before. 
A NIM-size pulse is split, with one path running directly to the scope (large pulse at left) and the other running down the PMT cable. Before the splice, the reflection from the open end returns to the scope 365 ns later (pulse on right).
scope1.jpg
Testing splice 2-1B: after. Because the PMT base is back-terminated, with the splice complete the reflection nearly vanishes. (There is a slight impedance mismatch between the long teflon cable and the PVC pigtail on the base.)
scope2.jpg
First row of optical barrier panels (for main PMT row 4) in. (Overlap strips not yet mounted.)
MVC-453X.JPG
Veto cluster behind OB panel. Click here for a much better picture taken Mar 15.
MVC-456X.JPG

Feb 26-Mar 2: More hardware.

More splicing, on a better table.
mvc-457x.jpg
The central shaft of the scaffolding.
Mvc-459xadj.jpg
Top lat restored after height adjustment; row 5 of panels started; cables routed through panels.
Dsc00003.jpg
Bill Groom mounting row 3 panels.
Dsc00007.jpg
Row-3 panel with light-baffled oil port.
Dsc00008.jpg
Other side of oil port/light baffle.
Dsc00016.jpg
Cable feedthrough.
Dsc00010.jpg
Cable teasing.
Dsc00021.jpg
Row 3-5 panels.
Dsc00009.jpg
Rows 3-6,8 showing panel clamps and PMT mounting blocks
Dsc00023.jpg

Mar 12-16: Install main (rows 3-6) and veto (row 3) PMT's in upper level.

Stan waiting for first box of main PMTs.
P1010037.JPG
Bill installing the first main tube, 3-1M.
P1010065.JPG
First main tube in place!
P1010068.JPG
Ryan self-portrait in 3-1M.
P1010072.JPG
First installed row: main row 3.
P1010076.JPG

 

Bill Sands.
P1010082.JPG
Mike Leung
P1010087.JPG
Rows 3 and 4 installed.
P1010089.JPG
Scaffold deck lowered before continuing PMT installation.
P1010096.JPG
Main rows 3-6 in place.
Dsc00038a.jpg

Mar 17-23: Install main row 7, test installed tubes, remove top scaffold deck.

Main rows 3-6 in place.
Dsc00006a.jpg
Andrew and Bill splicing row 7.
Dsc00008a.jpg
Main rows 3-7 in place.
Dsc00017a.jpg
Main rows 3-7 in place.
Dsc00019a.jpg
Andrew and Bill after a long day.
Dsc00021a.jpg
Fernanda, communing.
Dsc00022a.jpg
Peter posing.
fnal_01-319-3a.jpg
  

Mar 26-30: Install hardware, veto row 4.

Veto row 4.
Dsc00033a.jpg
Splicing veto row 4.
Dsc00034a.jpg
"Boxing ring" tower.
Dsc00035a.jpg
Neil and Peter splicing.
Dsc00037a.jpg

Apr 2-6: Install main rows 8-10.

Marching down the sphere.
 

 

Stan as you've never seen him.
Bill and Hayes lowering scaffolding.

Apr 9-13: Working on main rows 11, 12.

QT racks.
Bill Louis prepping panels.
Two pictures from the Fermilab photographer.
 

Apr 16-20: Splice main rows 11, 12.

Apr 23-27: Install veto row 5, most of main row 13.

Apr 30-May 4: Finish main row 13, install 14. Lead elements reach equator!

Crossing the equator!. (The row of veto bosses is on the equator.)
pm3a.jpg
View from the equator.
Sabina prepping cables for splicing.
Lyuda and Galina prepping cables.
Andrew and Sabina
Hayes doing last-minute cleanup before we remove the central tower.

May 7-11: Install veto row 6, most of main row 15.

May 14-18: Crossing the equator: install rest of main row 15, all of 16, 17.

May 21-25: Install main row 18, most of 19.

May 28-Jun 1: Install rest of main row 19.

 

Jun 4-8: Install veto row 7. most of main row 20.

I finally borrowed a tripod!
pdm_neg15a.jpg
 
pdm_neg12a.jpg
 
pdm_neg16.jpg
 
pdm_neg8.jpg

Jun 11-15: Install rest of main row 20, all of row 21. Return half of scaffold

Looking down through tophat.
assorted1.JPG
First truckload of scaffolding departing.
truck4.JPG

 Jun 18-22: Install main rows 22, 23, 24 and veto row 8

Jun 25-29: Install main row 25 and most of 26.

 Jul 2-6: Off

Jul 9-13: Install rest of main row 26, all of 

main row 27 and veto row 9, most of main row 28 (leaving a gap over the manhole.).

 

A beautiful shot of the main and veto tubes.
june01a.jpg
A sweeping view of the main tube array.
june02a.jpg
Under the bottom deck.
neg58-10a.jpg
Ryan and Hayes removing the last scaffolding.
neg58-12a.jpg
Andrew entering through left-out panels.
june03a.jpg
Ryan tidying up.
neg58-20a.jpg
Ryan, Peter, and Hayes at the South Pole.
neg58-21a.jpg
 
signa.jpg

Jul 16-20: Install main rows 29 and 30 (with gaps for access) and veto row 10. Ready for polar cap endgame.

A view up through the manhole. No scaffolding!
june21a.jpg
Looking down through the tophat.

 

june28.JPG
South polar region, ready for polar cap, which will hold main rows 32 and 33 and veto 11. We left out row 31 to allow walk-around access for installing the cap and the hanging laser flasks.
june22.JPG
The exit strategy. Panels and tubes in rows 28-30 were skipped to allow access through the manhole.
june25.JPG
Frank by the tank lid.
june32.JPG
Last truck of scaffolding on its way home.

 

june33.JPG

 

 

 

A nice one from the pros -- Fred Ullrich/FNAL.
01-696_4x6.jpg

 

  

Aug 20-24: The endgame begins. Install LSU laser flasks.

Laser flask.
augsep05b.jpg
Ryan and Morgan with the catch of the day.
augsep07a.jpg
Hayes advising Peter.
augsep08a.jpg
Fishing out cables to hang flasks.
monkey03a.jpg
Lowering a laser flask.
augsep09a.jpg
Morgan lowering a flask.
augsep11a.jpg
Laser flasks -- hanging.
endgame17a.jpg
Laser flask -- flashing. (Click for larger picture.)
endgame14a.jpg

Sep 4-7: Install North Polar Cap with LSU scintillator cubes. Install South Polar Cap and main row 31.

 

North polar cap (NPC) -- bare.
endgame18a.jpg
NPC with PMTs and LSU scintillator cubes on rods. Note that the shallowest cube is mounted on a can that blocks light from behind the PMTs.
endgame22a.jpg
North polar cap (NPC) -- loaded.
endgame32a.jpg
The endgame crew. Front (l-r): Morgan Wascko, Peter Meyers. Rear (l-r): Richard Imlay, Ryan Patterson, Andrew Bazarko, Bill Sands. (Not present: Hayes Lansford, Myungkee Sung, Aaron McMorris)
endgame28a.jpg
Ryan preparing the tophat.
neg60-16.jpg
  
Installing the NPC. Move it across tophat.
endgame33a.jpg
With the NPC over the tophat, Ryan, Morgan, Andrew, and Richard deploy the deepest cubes. The 1 m cube's rod is folded down, the 2- and 3-m cubes are lowered on their (common) hanging cable.
neg60-21.jpg
Lowering into place.
endgame36a.jpg
The North Pole with NPC in place. Note: all flasks and cubes visible in this image.
neg60-25a.jpg
Reopening the southern front. The South Polar Cap (SPC) minus its center disk, showing the bottom veto cluster on the concentric fill pipe.
neg60-17a.jpg

 

SPC with PMTs in place.
neg60-24a.jpg
Closeup, showing PMT mount and oil baffle on concentric fillpipe.
endgame39a.jpg
The South Pole -- complete. The vertical wires tension the hanging laser flasks and scintillator cubes.
endgame42a.jpg

Oct 17-20: Final in-tank installation: top veto cluster and 10 main tubes around manhole, seal top lid.

North polar cap without and with top veto cluster.
october01a.jpg
 
october04a.jpg
Nice view of hanging flask.
oct00006.jpg
Temporary manhole cover with ventilation.
oct00012.jpg
Last look through manhole.

 

october16a.jpg
View of manhole disk from inside.
oct00015.jpg
Bill ready to receive last panel.
oct00020.jpg
Ryan handing in last tube to Bill.
oct00031.jpg
Bill installing last tube.
oct00032.jpg

 

Last panel with tubes.
october20a.jpg
Done! Last panel in place.
oct00038.jpg

 

  
Top disk in place: completes tank sphere in tophat. Cables penetrating disk are optical fibers from scintillator cubes.
oct00041.jpg
Tophat region, showing 1521st tube. Also visible: cable feedthru, oil-level probe, feedthru panel for N2 and temperature signals.

 

oct00042.jpg